Surface Treatment Update for Tunbridge Wells and Maidstone 22nd July 2013
Just a reminder of this and next week’s work in West and East Farleigh, and the works programmed in September.
Maidstone
Lower Road, East and West Farleigh – Ironwork adjustment following microsurfacing earlier this year. (Up to 2 weeks duration)
This is a mixture of stop/go boards and road closures with local diversions.
1st week commencing 22/7/13 to 26/7/13 this will be controlled with temporary traffic management (stop/go boards)
2nd week starting 29/7/13 to Friday 2/8/13
Road closure between Vicarage Road and Kettle Lane(29/7/13 to 1/8/13)
Road closure between Ewell Lane and Teston Lane(2/8/13)
(School holidays start 25/7/13)
Extra works in September :
Maidstone – Microsurfacing
BUCKLAND ROAD, MAIDSTONE (Between Buckland Hill and Schools) – Saturday 14th September (Road closure with access using stop/go boards)
GOUDHURST ROAD, MARDEN – 15/9/13 (Stop/go boards)
A229 STAPLEHURST ROAD STAPLEHURST – 15/9/13 (Stop/go boards)
Tunbridge Wells – Microsurfacing
BUBHURST LANE FRITTENDEN – 15/9/13 and 16/9/13 (Stop/go boards/Road closure)
THE STREET BENENDEN – 17/9/13 (Stop/go boards)
MOUNTS HILL BENENDEN – 15/9/13 (Stop/go boards)